在周六停电影响了大约130,000名用户后,旧金山成千上万的商业和住宅继续恢复供电,根据太平洋煤气公司的说法&电气公司(第&e)。
据宝洁公司称,停电是由一个变电站的火灾引起的&E.
到周日早上,大约110,000用户的电力已经恢复&e说。其余的21,000名客户主要位于金门县里士满区的Presidio公园和小区域市中心据公用事业公司说,是旧金山。
虽然对变电站的破坏是“重大的”和广泛,“没有对PG造成伤害&工人或公众,第&e说。
“我们变电站的火灾造成了巨大的损失,修复和安全恢复将非常复杂。我们将继续工作,直到所有顾客都得到恢复,”第&e在一个下午早些时候说更新星期天。“我们鼓励客户注意安全。”
据宝洁公司称,第一次断电是在周六下午1点左右&下午4:30电网稳定,停止任何额外的停电。消防官员在下午6点控制了变电站的火势,根据三藩市美国广播公司KGO站。
停电发生在城市挤满游客和假日购物者的时候。由于交通信号仍然不起作用,电力的缺乏使整个受灾地区的交通陷入混乱。
旧金山监事会成员马特·多尔西告诉《KGO》:“从历史上看,圣诞节前的周六是一年中最繁忙的购物日之一。”。“这是PG最糟糕的时候&e可能会有问题。"
据宝洁公司称,变电站火灾的原因仍在调查中&E.
Power nearly restored in San Francisco after widespread outage Saturday
Power continues to be restored to tens of thousands of San Francisco businesses and residences following a Saturday outage that affected some 130,000 customers,according to Pacific Gas&Electric Company(PG&E).
The outage was caused by a fire at an electrical substation, according to PG&E.
By Sunday morning, power had been restored to about 110,000 customers, PG&E said. The remaining 21,000 customers were located primarily in the Presidio, Richmond District, Golden GateParkandsmall areasof downtownSan Francisco, according to the utility.
While the damage to the substation was "significantandextensive," there were no injures to PG&E workers or the public, PG&E said.
"The damage from the fire in our substation was extensive and the repairs and safe restoration will be complex. We will continue working until all customers are restored," PG&E said in an early afternoonupdateSunday. "We encourage customers to be safe."
The first outages were reported at around 1 p.m. Saturday, according to PG&E, with the grid stabilized by 4:30 p.m., halting any additional outages. Fire officials brought the substation fire under control by 6 p.m.,according toSan Francisco ABC station KGO.
The blackout occurred when the city was teeming with tourists and holiday shoppers. The lack of power snarled traffic throughout the affected areas as traffic signals remained inoperative.
"The Saturday before Christmas is historically once of the busiest shopping days of the year," San Francisco Board of Supervisors member Matt Dorsey told KGO. "This is the worst time that PG&E could have a problem."
The cause of the substation fire remains under investigation, according to PG&E.